Sr. No
|
FACTOR
|
CONVENTIONAL
|
IN
– SITU ALUMINIUM FORM SYSTEM
|
REMARKS
|
|
1
|
Quality
|
Normal
|
Superior. In –
Situ casting of whole structure and transverse walls done in a continuous
operation, using controlled concrete mixers obtained from central batching,
mixing plants and mechanically placed through concrete buckets using crane
and compacted in leak proof moulds using high frequency vibrators
|
Superior quality in “System housing”
|
|
2
|
Speed of construction.
|
The pace of construction is
slow due to step – by – step completion of different stages of activity the
masonry is required to be laid brick by brick. Erection of formwork,
concreting and deshuttering forms is a two – week
cycle. The plastering and other finishing activities can commence only
thereafter.
|
In this system, the walls and
floors are cast together in one continuous operation in matter of few hours
and in built accelerated curing overnight enable removal and re-use of forms
on daily cycle basis.
|
System construction
is
much
faster.
|
|
3
|
Aesthetics.
|
In the case of RCC structural
framework of column and beams with partition brick walls is used for
construction, the columns and beams show unsightly projections in room
interiors.
|
The Room – Sized wall panels
and the ceiling elements cast against steel plates have smooth finishing and
the interiors have neat and clean lines without unsightly projections in
various corners. The walls and ceilings also have smooth even surfaces, which
only need colour/white wash
|
|
|
4
|
External
finishes.
|
Cement
plastered brickwork, painted with cement – based paint. Finishing needs
painting every in three years.
|
Textured
/ pattern coloured concrete facia can be provided. This will need no frequent
repainting.
|
Permanent
facia finishes feasible with minor extra initial cost
|
|
5
|
Useful
carpet area as % of plinth area.
|
Efficiency
around 83.5%
|
Efficiency
around 87.5%
|
More
efficient utilization of land for useful living space.
|
|
6
|
Consumption of basic raw
materials
Cement.
Reinforcing Steel
|
Normal
Reinforcing steel required is
less as compared to the in situ construction as RCC framework uses brick wall
as alternative
|
Consumption somewhat more than
that used in conventional structures.
It may, however will be
slightly more than corresponding load – bearing brick wall construction for
which, requirements of IS 456 have to be followed for system housing.
|
Although greater consumption
strength and durability is also more
Steel requirement is more, as
it is required for the shear wall construction. But shear wall construction
increases safety against earthquake.
|
|
7
|
|
Maintenance
|
In maintenance cost, the major
expenditure is involved due to :
· Repairs and maintenance
of plaster of walls / ceiling etc.
· Painting of outer and
inner walls.
Leakages due to plumbing and
sanitation installation.
|
The walls and ceiling being
smooth and high quality concrete repairs for plastering and leakage’s are not
at all required frequently.
|
It can be concluded that
maintenance cost is negligible.
|