Economics of MIVAN formwork

 

 

 

Table 3.8.2: - Effect of construction speed on the cost of flat.

(Courtesy: Jogeswari Vikhroli link road, NNP Nivara Parishad,MMRDA)

 

 

Description

Construction Speed

A

B

C

D

Construction speed

3 flats/day

4 flats/day

5 flats/day

6 flats/day

Period of const.

23 months

18.7 months

16.2 months

14.2 months

Forming area

741.9

989.2

1236.5

1483.8

Misc formwork

55.5

55.5

55.5

55.5

Total formwork to be ordered

797.4

1044.7

1292

1539

Cost of formwork

14353200

18804600

23256000

27707400

Two third of the loaded cost

9568800

12536400

1550400

18471600

Profit & Overhead 15%

1435320

1880460

2325600

2770740

 

Total Rs.

11004120

14416860

17829600

21242340

Cost per flat, Rs

9825

12872

15919

18966

 

Note:

Construction period is calculated as follows:

Average 22 pouring of concrete are considered per month.

About 3 months are required for mobilization and getting plinths ready.

About 3 months are required for finishing.

Cost of formwork = $ 360; dollar Exchange Rate = Rs50; No of flats = 1120

(Weight of aluminium formwork = 24 kg/m²).

 