Economics of MIVAN formwork
Table
3.8.2: - Effect of construction speed on the cost of flat.
(Courtesy: Jogeswari Vikhroli link road, NNP Nivara Parishad,MMRDA)
|
Description |
Construction Speed |
|
A |
B |
C |
D |
|
Construction speed |
3 flats/day |
4 flats/day |
5 flats/day |
6 flats/day |
|
Period of const. |
23 months |
18.7 months |
16.2 months |
14.2 months |
|
Forming area |
741.9 |
989.2 |
1236.5 |
1483.8 |
|
Misc formwork |
55.5 |
55.5 |
55.5 |
55.5 |
|
Total formwork to be ordered |
797.4 |
1044.7 |
1292 |
1539 |
|
Cost of formwork |
14353200 |
18804600 |
23256000 |
27707400 |
|
Two third of the loaded cost |
9568800 |
12536400 |
1550400 |
18471600 |
|
Profit & Overhead 15% |
1435320 |
1880460 |
2325600 |
2770740
|
|
Total Rs. |
11004120 |
14416860 |
17829600 |
21242340 |
|
Cost per flat, Rs |
9825 |
12872 |
15919 |
18966 |
Note:
Construction period is calculated as follows:
Average 22 pouring of concrete are considered per month.
About 3 months are required for mobilization and getting plinths ready.
About 3 months are required for finishing.
Cost of formwork = $ 360; dollar Exchange Rate = Rs50; No of flats = 1120
(Weight of aluminium formwork = 24 kg/m²).